River Crossing, Toulouse, France
November 22, 2022 by admin
Filed under Prime Blog
Ariege River Crossing
Tracking used: #ParaTrack2 & #GyroModule
Distance: 609.46 m
Depth: 26 m
Entry Angle: 12.1
Exit Angle: 17.5
Ground: Medium hard, sandstone
Pipeline: Steel 300mm
Technique: #MudMotor
Job Description: The job included 2 parallel bores, separated 5m away from each other. The 300 mm pipe was for gas. Depth below entry point was 26m, and we were drilling 64m deep below a steep hill in the middle of the bore.
Read more on LinkedIn.
One of the largest tidal stream energy in the world
November 9, 2022 by admin
Filed under Prime Blog
#InnovationandExperience #HDD
HDD innovation and experience
November 3, 2022 by admin
Filed under Prime Blog
Did you know Prime Horizontal provides #ABIA (At Bit Inclination Assembly), #ParaTrackGyroModule, guidance, downhole tooling, & #ProData rig recording system?
Drop us an email or give us a call if you’d like to speak with a representative from your local Prime Horizontal branch to explore how we may be able to help each other now or in the future.
We are looking forward to working with you.