Longest Intersect in India!

July 7, 2021 by  
Filed under Prime Blog

#Congratulations to the team involved in the #Longest Intersect in India!
#RemoteSupport by Prime Horizontal Europe out of India.

HDD and Associated works for Brahmaputra River under Barauni-Guwahati Pipeline Project 1
Tracking used: #ParaTrack2
Location: Guwahati, Assam, India
Distance: 3,558.74m (11,674ft)
Depth: 41.5m/ 136ft
Horizontal Curve: 3,565.14 m (11,696ft)
Entry Angle: 10 degree
Exit Angle: 10 degree
Ground: Rock and soft
Pipeline: 6”
Tracking used: Wire line & ParaTrack2
Technique: #MudMotor assembly and #Jetting assembly
Job Description: HDD across Brahmaputra River under BGPL Project

#teamworkmakesthedreamwork #kudos #HDD
https://lnkd.in/ep5RX2Z

2
3

Jumbo Viper RockReamers – Now Internationally Available!

July 2, 2021 by  
Filed under Prime Blog

Viper Jumbo RockReamer

Prime Horizontal is proud to announce that we are the global suppliers of Viper & Jumbo Rock Reamers!

Contact your local Prime Horizontal office:

Prime Horizontal B.V.
Salland 3
1948 RE Beverwijk
The Netherlands
PHONE: +31 251 271 790
FAX: +31 251 271 064
EMAIL:  office@primehorizontal.com
Prime Horizontal, Inc
7710 Harms Road
Houston, TX 77041
U.S.A.
PHONE: +1 346 998 1180
FAX: +1 346 998 1190
EMAIL:  officeusa@primehorizontal.com
Prime Horizontal
Australia Pty Ltd
10 Enterprise Street, Cleveland, QLD 4163, Australia
PHONE: +61 73 821 3684
EMAIL:  officeau@primehorizontal.com

 

Underwater work for water facility in Pierre, South Dakota.

May 11, 2021 by  
Filed under Prime Blog

Screen Shot 2021-05-04 at 19.58.49 Screen Shot 2021-05-04 at 19.59.03

Congratulations Prime Horizontal #America on the underwater work for water facility in Pierre, South Dakota.!
Tracking used: #ParaTrack2
Location: Pierre, South Dakota
Distance: 720ft.
Depth: 26ft.
Entry Angle: 11 degrees
Exit Angle: 90 degrees
Pipeline: 4 inch HDPE SDR 7 inside of 24 inch PVC #pipe
Technique: Land to River
#SurfaceCoil with the help of divers laying coil on the river bottom.
The project was designed to bring drinking #water from the Missouri River to the city of Pierre, SD. Our engineer had to stay within tight tolerances to keep the product pipe inside the installed Caisson. Central Trenchless was our client for the project and Shaun Houim, owner of Central Trenchless, was elated to see the results of the project.
Local newspaper coverage:
Click here to read article written by mayor of Pierre, SD.

 

 

 

 

 

Got Rollers?

May 5, 2021 by  
Filed under Prime Blog

Pipe Rollers
pipe rollers
Contact the Prime Horizontal Inc team to get your hands on these top-notch Large #HDD Pipe Rollers!
Prime Horizontal Inc,
7710 Harms Road,
Houston,
TX 77041
Phone: +1 346 998 1180
Email: officeusa@primehorizontal.com
#morethanguidance #HDD #PrimeHorizontal

 

Highway 61 crossing

March 30, 2021 by  
Filed under Prime Blog

Kudos to Challenger Drilling Inc. & Prime Horizontal America on the #successful Gyro Module guided Highway 61 crossing

https://www.linkedin.com/posts/prime-horziontal_kudos-primehorizontal-america-activity-6782725105563836416-mSS2

Location: Baton Rouge, LA
Tracking used: #GyroModule combined with the #ACBeacon
Distance: 1764 ft (538m)
Depth: 100ft (30m)
Product Pipe: 2 x 8” steel
Entry/Exit Angle: 12/6
Technique: Highway & Railroad Crossing

Job difficulty was high as this is a congested #pipeline corridor with numerous existing pipelines. Access to the crossing & job site was done by air boat as project was surrounded by swamp/marsh. No surface coil was used, instead the Gyro Module was the primary source of guidance, with the AC Beacon confirming the drill location under Highway 61.

#hdd #job #teamworkmakesthedreamwork
image013

 

 

 

40’’ Barrel Reamer

March 29, 2021 by  
Filed under Prime Blog

#PrimeHorizontal: not only Guidance , Gyro Modules and Intersects: Introducing this beauty that was sent out; 40’’ #BarrelReamer with Hardox 400 wear protection added on to standard hard facing.

Reamer-3Reamer-1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

#hdd #design #teamworkmakesthedreamwork

 

NASTT No-Dig Show 2021

March 26, 2021 by  
Filed under Prime Blog

Come and talk to #PrimeHorizontal @ #NASTT look for Rodrigo and Christian who will be visiting from the 29th til the 31st of March.

See you there!

NASTT_2021

 

 

 

 

 

 

 

 

 

 

https://www.linkedin.com/feed/update/urn:li:activity:6781239115384967168

Taichung Harbour Intersect Crossing, Taiwan

March 16, 2021 by  
Filed under Prime Blog

One more for the #PrimeHorizontal #Australasia team on the Taichung Harbour Intersect Crossing

Taichung harbor crossing1

Technique: #Intersect
Tracking used: Gyro Module & #ParaTrack2 and AC Beacon
Location: Taichung Taiwan
Distance: 1367m
Depth: 40m
Horizontal Curve: 1500m
Entry Angle: 12deg
Exit Angle: 10deg
Ground: Cobble, Clay and Sand
Pipeline: 36” steel pipeJob Description:
Taichung harbor crossing2The crossing was completed by Intersect method, using the ParaTrack Gyro Module drilling from the south (1097m) and underground coil drilling from the North, at which point the #ParaTrack Steering Tool was in range of the AC Beacon and surface coil. The intersect was completed without any ranging due to the vertical and horizontal accuracy of the #GyroModule, #Beacon and surface coil tracking combination.
#hdd
#success
#teamworkmakesthedreamworkTaichung harbor crossing3

Throwback: Gyro Module job in Plock, Poland end of 2020

February 24, 2021 by  
Filed under Prime Blog

#PrimeHorizontal #Europe

Throwback Thursday #successtory to end 2020:

Gyro Module job in Plock, Poland

Tracking used: #GyroModule, #ParaTrack2 and Pressure Whilst Drilling (#PWD)

Plock_1

Distance: 698m (2,290’)

Water distance: 534m (1,750’)

True Vertical Depth: 41 m (134’)

Cover under riverbed: 27 m (88’)

Entry coil: 43m (141’)

Exit coil: 110m (360’)

Formation: Clay

BHA: Motor Assembly (Mud motor 6 ¾” + 12 ¼” bit)

Plock_2

This complex project started with a 2 degree bend setting on a 6 ¾” mud motor, and a 12 ¼” bit. The ground was variable initially which caused the usual issues, eventually as we drilled along the profile the adjustable bent housing allowed us to change the motor bend, to 2.24 degrees, on the job site to be more aggressive.

The predominant formation was clay.

The project was designed to cross under the Largest Polish river whilst utilizing the pressure whilst drilling throughout the complete crossing for monitoring returns.

Crossing length 698m. 6m long drill pipes 5″ and on a 600KN Rig.

The Pilot Hole was #successfullycompleted with great teamwork and experience, which enabled us to complete a job with a #great result.

#teamworkmakesthedreamwork #hdd

 

N-Net Japan PGM project

February 23, 2021 by  
Filed under Prime Blog

#Kudos to #PrimeHorizontal #Australasia
N-Net Japan PGM project: Observation Network for Earthquakes & Tsunamis

Distance: 773m
Depth: 82m
Entry/ Exit angle: 20°/ 10°
Horizontal curve: 23.4°
Product Pipe Installed: Drill pipe 5”
Tracking used: #ParaTrack #GyroModule, surface coil & #ACBeacon (BTS)
Technique: 6 ¾” Mud motor (Outfall)

N-Net Japan PGM pic3

We were required to drill the pilot bore from the top of the mountain through a 2m steel circular intermediate shaft, 48m below Entry elevation located at shoreline 132m away from the entry point, the intermediate shaft was required to control the mud pressure whilst drilling below the seabed. After running steel casing from entry to intermediate shaft, Pilot drilling continued drilling 641m out to sea turning 23.4° before punching out on the seabed with a 10° exit angle.

N-Net Japan PGM pic2

A 60m surface coil in combination with the #BTS (AC Beacon) was used as secondary tracking between the entry point and the intermediate shaft to confirm the elevation before continuing through the shaft to exit. The ParaTrack Gyro Module was utilized from entry until punch out on the sea Floor, exit position was verified by Divers and the DHA removed 16m below sea level.