Edmonton Legislature Building- Power Upgrade
September 7, 2022 by Joseph
Filed under Prime Blog
Short ones are the tricky ones.
Tracking used: #ParaTrack2
Location: Downtown Edmonton, Alberta, Canada
Distance: 250m (820 ft)
Depth: 20m (66 ft)
Horizontal Curve: 19.23deg
Entry Angle: 13deg
Exit Angle: 4deg
Ground: Sand/Gravel/Clay
Pipeline: 18inch HDPE
Technique: #MudMotor (90%) and #Jetting (the last 10%)
We were contacted to do a special project for which was #complex in nature. The project was in the hustling bustling downtown area of Edmonton City.
A Power #Upgrade required 2 power lines to be installed under the Alberta Legislature Grounds. Both drills were designed to have 4m lateral separation. Tight spaces were the prime feature of this job.
An entry pad was specially built which could only accommodate the drill rig & nothing else. The Exit point was located 3 floors down in a Car Park. 32-inch-wide holes were tactically drilled out of the concrete of the parking wall, to enable the BHA to poke through.
There was no room for error. The challenge was accepted and both times we hit the target dead center. The combination of compound curves and constantly changing ground geology added to the challenge. Together with the dedication and teamwork of Omni Directional Boring LP and Prime Horizontal, both bores were completed, and the product was pulled in safely.
#ThankYou for the mention
#innovationandexperience #teamworkmakesthedreamwork
Casselman on Sat, 29th Oct 2022 5:45 am