Prime Intersect Team Pushing the boundaries!
Precision in Action: Shortest HDD Intersect Yet
Successful HDD Intersect in France – Our Shortest Intersect Thus Far!
Rainbow ending at the job site
| Tracking used: | Intersect |
| Location: | Castelsarrasin (France) |
| Distance: | 196.38m |
| Depth: | 16m |
| Entry Angle: | 15deg |
| Exit Angle: | 15deg |
| Ground: | Clay |
| Pipeline: | 250mm HDPE sleeve. Product pipe 160mm HDPE |
| Technique: | Jetting |
| Was it an Intersect/CBM/River crossing: | Intersect under railway tracks |
| What would the end use be for?: | Gas |
An accurate intersect was required to cross two railway tracks, due to ground conditions made an intersect the best option. Casings were installed on both sides to avoid a gravel layer, with an entry casing of 30 meters and an exit casing of 24 meters.
The design allowed only a 35 meters of straight alignment window beneath the railway tracks to achieve the intersect.
The operation proceeded smoothly, resulting in a successful intersect.
At 196.38m long, probably the shortest intersect to date!

#PrimeHorizontal #TheOriginalIntersectCompany #HDD #Innovation #InnovationAndExperience #Catalana de Perforacions #Terega